Calgary has reached a major milestone in its efforts to resolve the water infrastructure problems that have disrupted residents and businesses since 2024. Municipal officials announced Thursday, November 26, that construction of the new Bearspaw South Feeder Main is complete and that the replacement pipe has been connected to the city's water distribution network. The announcement follows approximately 11 months of accelerated construction, although further testing is required before the new infrastructure can begin carrying drinking water.

The replacement project covers approximately 6.5 kilometres of pipe. Construction involved underground tunnelling between the Shaganappi Pump Station and 73 Street N.W., followed by open-cut construction through portions of Bowness. The project was accelerated after major failures of the existing feeder main in June 2024 and December 2025 exposed vulnerabilities in Calgary's water distribution system.

Municipal officials are now preparing to commission the replacement pipe. That process includes pressure testing, cleaning, flushing and confirming that the water meets applicable quality requirements. The city expects the new infrastructure to become operational later in December. In the meantime, Calgary intends to temporarily return the original feeder main to service, with refilling expected to take about five days. City officials estimate the refill will require approximately 22 million litres of water.

If that process proceeds successfully, the municipality expects to lift its current water restrictions later next week. The city continues to publish traffic detours and road-closure updates for the area around Parkdale Boulevard.

For Calgary residents, Thursday's announcement marks the transition from construction to operational readiness. Stage 4 outdoor water restrictions remain in effect, and residents are still being asked to conserve water indoors. The completion of construction does not mean the replacement feeder main is already operating. The next major milestones will be the temporary restoration of the original pipe, the removal of restrictions and the successful commissioning of the replacement infrastructure.

Sources: LiveWire Calgary’s coverage of the city briefing; City project and traffic updates.