Calgary has reached additional construction milestones as crews work to connect the new Bearspaw South Feeder Main to the city's water distribution network. Municipal officials announced Tuesday, November 24, that the pipe connection at the Shaganappi Pump Station has been completed and inspected. The connection is ready to receive water, while crews anticipate beginning recommissioning work at several repaired pipe locations on Wednesday. Construction remains on schedule across the active worksites, according to the city's latest update.
Crews working near 89 Street and 33 Avenue N.W. have installed and connected a major steel junction that will link the new feeder main with existing infrastructure leading to the Bearspaw Water Treatment Plant. Further welding and connection work remains underway. Additional excavation and pipe work continue near 83 Street and 33 Avenue.
Along Parkdale Boulevard and Memorial Drive N.W., installation work has been completed at five locations. Crews are restoring the affected construction areas, and the city expects to begin recommissioning those pipes November 25. The latest progress moves Calgary closer to restoring normal water distribution operations, although the anticipated recommissioning represents a scheduled next step rather than confirmation that all repaired infrastructure has returned to service.
Regional water consumption reached 489 million litres Monday, remaining below the municipality's daily conservation target of 500 million litres. Calgary and neighbouring communities have consistently remained within the desired range during the current connection work. Maintaining lower consumption helps preserve operational flexibility while the city's ability to transfer water through the distribution system remains temporarily constrained.
The city also provided an update on its conditional exemption allowing WinSport to use municipal water for snowmaking. Although the facility received permission Monday to use up to three million litres per night, it produced only a limited quantity of artificial snow during the first night because temperatures were unsuitable. Municipal officials expect warmer conditions to restrict further opportunities over the next several days. The exemption remains conditional on stable water supplies and acceptable regional consumption.
Stage 4 outdoor water restrictions continue to apply across Calgary. Residents and businesses should not interpret the completed inspection, planned recommissioning or WinSport exemption as confirmation that general restrictions have ended. The municipality must complete the remaining connections and establish safe operating conditions before announcing changes to water-use requirements. The next important milestones are successful recommissioning at the repaired locations, completion of the remaining feeder-main work and confirmation of the system's readiness to return to normal service.
Sources: City of Calgary: November 24 feeder-main update · City of Calgary: Stage 4 water restrictions